Project Cost Estimation
 
Published: 16 Feb 2007
Abstract
Software Project Estimation is a very important aspect of Project Management. It is one of the most crucial and challenging aspects. This article examines the various aspects involved with estimating project costs.
by Arindam Ghosh
Feedback
Average Rating: 
Views (Total / Last 10 Days): 134382/ 90

Introduction

Project cost management may be defined as management of the processes involved in planning, estimating, and controlling costs so that the project can be completed within the approved budget.

·         Cost Estimating

·         Cost Budgeting

·         Cost Control

Cost Estimating

Approximate costs are developed for complete schedule activities after consideration of risks and all causes of risks and possible cost variation. This quantitative assessment process generates a Schedule Activity Cost Estimate.

Various alternative estimates are identified and considered. All additional costs are checked for justification in additional savings in the life cycle process. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations.

Resources for which costs are estimated include infrastructure, labor, materials, equipments, etc. and special categories like inflation or contingency. If the performing organization does not have formally trained project cost estimators then the project team will need to supply both the resources and the expertise to perform project cost estimating activities.

Type of Costs

There are different ways to look at the costs while estimating and controlling project costs.

A cost is either variable or fixed.

Variable Cost

A variable cost is any costs that change with the amount of production or the amount of work. Example: cost of materials, power, water and wages.

Fixed Cost

Cost that does not change as production changes is a fixed cost. Example: set up cost, rental or hiring of an equipment or machinery.

A cost can be either direct or indirect.

Direct Cost

Costs are directly attributable to the work on the project. Example: team travel, team wages, recognition, and costs of materials used on the project.

Indirect Cost

Overhead items or costs incurred for the benefit of more than one project are indirect costs. Example: Corporate Tax, Fringe Benefit Tax, and House keeping Services including security services.

Opportunity Cost

The Opportunity given up by choosing a choice of project over another project is an opportunity cost. For example, if we need to select one of the following two projects:

-Project A with an NPV $60,000

-project B with an NPV $50000

then opportunity cost of selecting Project A is $50,000.

Sunk Cost

Sunk costs should not be considered when deciding on reviving or continuing with a troubled project. Sunk costs are the ones which were already spent on the project earlier and will not be considered when the revival plan decision is made.

Tools and Techniques of Cost Estimating

Analogous Estimating

Analogous cost estimating means using the actual cost of previous or similar projects as the basis for estimating the cost of the current project.

Analogous cost estimating

This is used when there is a limited amount of detailed information about the project.

It uses expert judgment, is less expensive and is less accurate but reliable in similar project situations.

Determine Resource Cost Rates

Actual per unit human and material resource rates are collated or estimated.

Quotes, contracts, commercial database, seller published price lists are used and appropriate

Escalation rates and inflation are incorporated.

Bottom-up Estimating

Individual schedule activities are estimated to the smallest detail. All costs are then aggregated and used for reporting, tracking and control purposes. Here, the individual activity cost consciousness is of prime importance.

Parametric Estimating

This technique uses historical cost with current project variables that are determined. This is a highly accurate method as it requires clarity in current project variables.

Project Management Software

Widely Available cost estimation applications can be used for faster estimation of alternatives.

Vendor Bid Analysis: Vendor Bid analysis is another technique to benchmark costs. If a project is won in a competitive bid, more details may be considered for cost estimation and control purposes.

Reserve Analysis

Reserves or Contingency allowances are used to deal with uncertainty or “knowns-unknowns” and these are added to the cost estimates, thus sometimes overstating project costs.

Options vary between grouping similar activities and assigning a single contingency reserve for that group to a zero duration activity. This activity may be placed across the network path for that group of schedule activities. As the schedule progresses, the reserve can be adjusted.

Creating a buffer activity in the critical chain method at the end of the network path as the schedule progresses, allows the reserve to be adjusted.

Cost of Quality

Cost of quality can also be used to prepare the schedule activity cost estimate.

Cost Budgeting

Cost budgeting involves aggregating the estimated costs of individual schedule activities or work package to establish a total cost baseline for measuring project performance. The project scope statements are prepared prior to the summary budget. However, schedule activity or work package cost estimates are prepared prior to the detailed budget requests and work authorization.  

Tools and Techniques of Cost Budgeting

Cost Aggregation

Schedule activity cost estimates are aggregated and grouped by work packages, which may be then grouped by higher levels as per levels set by the WBS, then finally by the entire project.

Reserve Analysis

Reserves or Management Contingency allowances are used to deal with uncertainty –“known unknowns.” The reserve is added to the project budget, but not distributed as budget because they are not a part of earned value calculations.

Parametric Estimating

The parametric estimating technique involves using project characteristics (parameters) in a mathematical model to predict total project costs. Both the cost and accuracy of parametric models vary widely. They are most likely to be reliable when:

the historical information used to develop the model is accurate

the parameters used in the model are readily quantifiable

the model is scaleable, such that it works for a large project as well as a small one

Funding Limit Reconciliation

Funds are reconciled and based on the results and new limits are set and WBS components are adjusted. This may impact allocation of resources to the project. If costs are used in the schedule development process, the process is repeated with new constraints and a new baseline is derived.

Cost Control

Project cost control includes:

Influencing the factors that create changes to the cost baseline

Ensuring requested changes are agreed upon

Managing the actual changes when and as they occur

Assuring that potential cost overruns do not exceed the authorized funding periodically and in total for the project

Monitoring cost performance to detect and understand variance from the cost baseline

Recording all appropriate changes accurately against the cost baseline

Preventing incorrect, inappropriate, or unapproved changes from being included in the reported cost or resource usage

Informing appropriate stakeholders of approved changes

Acting to bring expected cost overruns within acceptable units

Project cost control searches out the causes of positive and negative variance and is part of the Integrated Change Control.

Tools and Techniques of Cost Control

Cost Change Control System

A cost change control system, documented in the cost management plan, defines the procedures by which the cost baseline can be changed. It includes the forms documentation, tracking systems, and approval levels necessary for authorizing changes. The cost change control system is integrated with the integrated change control process.

Performance Measurement Analysis

Performance measurement techniques help to assess the magnitude of any variance that will I invariably occur.  The earned value technique (EVT) compares the cumulative value of the budgets cost of work scheduled (planned) to the actual cost control, resource management, and production.

An important part of cost control is to determine the variance, the magnitude of the variance, and to decide if the variance requires corrective action.

The earned value technique uses the cost control contained in the project management plan to assess project progress and the magnitude of any variations that occur. The earned value technique involves developing these key values for each schedule activity, work package, or control account.

Planned value (PV)

PV is the budgeted cost for the work scheduled to be completed on an activity or WBS component up to a given point in time.

Earned value (EV)

EV is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

Actual cost (AC)

AC is the actual cost incurred in accomplishing work on the schedule activity or WBS component during a given time period. This AC must correspond in definition and coverage to whatever was budgeted for the PV and the EV (e.g. direct hours only, direct cost only, or all costs including indirect costs).

Estimate to complete (ETC) and estimate at completion (EAC)

The PV, EV, and AC values are used in combination to provide performance measures of whether or not work is being accomplished as planned at any given point in time. The most commonly used measures are cost variance (CV) and schedule variance (SV). The amount of variance of the CV and SV values tend to decrease as the project reaches completion due to compensating effect of more work being accomplished. Predetermined acceptable completion can be established in the cost management plan.

Cost Variance (CV)

CV equals earned value (EV) minus actual cost (AC). The cost variance at the end of the project will be the difference between the budget at the completion (BAC) and the actual amount spent.

Formula: CV=EV-AC

Schedule Variance (SV):

SV equals earned value (EV) minus planned value (PV). Schedule variance will ultimately equal zero when the project is completed because all of the planned values will ultimately equal zero when the project is completed because all of the planned values will have been earned.

Formula: SV=EV-PV

These two values, the CV and SV, can be converted to efficiency indicators to reflect the cost and schedule performance of any project.

Cost performance index (CPI)

A CPI value less than 1.0 indicate accost overrun of the estimates. A CPI value greater than 1 indicates a cost under-run of the estimates. CPI equals the ratio of the EV to the AC. The CPI is the most commonly used cost-efficiency indicator.

Formula: CPI=EV/AC

Cumulative CPI (CPI^c):

The cumulative CPI is widely used to forecast project costs at completion. CPIC equals the sum of the periodic earned values (EV^c) divided by the sum of the individual actual costs (AC^c).

Formula: SPI=EV/PV

The earned vale technique in its various forms is a commonly used method of performance measurement. It integrates project scope, cost (or resource) and schedule measures to help the project team assess project performance.

Forecasting

Forecasting includes making estimates or predictions of conditions in the project’s future based on the information and knowledgeable available at the time of the forecast. As the project progresses, the forecasts are adjusted.

The earned value technique parameters of BAC, actual cost (AC^c) to date, and the cumulative CPI^c efficiency indicator are used to calculate ETC and EA, where the BAC is equal to the total PV at completion for a schedule activity, work package, control account, or other WBS component.

Formula: BAC=total cumulative PV t the completion

Forecasting technique parameters to assess the cost or the amount of work to complete schedule activities is called the EAC. Forecasting techniques also help to determine the ETC, which is the estimate for completing the remaining work for a schedule activity, work package, or control account. While the earned value technique of determining EAC and ETC is quick and automatic, it is not as valuable or accurate as a manual forecasting technique based upon the performing organization providing the estimate to complete.

ETC is based on the new estimate. ETC equals the revised estimate for the work remaining as determined by the performing organization. This more accurate and comprehensive completion for all the work remaining considers the performance estimate to complete all the work remaining and the performance or production of the resource to date. 

Alternatively, to calculate ETC using value data, one of the two formulas is typically used:

ETC based on atypical variances. This approach is most often used when current are seen as atypical and the project management team expectations are that similar variance will not occur in the future. ETC equals the BAC minus the cumulative earned value to date (EVC).

Formula: ETC= (BAC - EVC)

ETC based on typical variances. This approach is most often used when current are seen as typical of future variances. ETC equals the BAC minus the cumulative EVC (the remaining PV) divided by the cumulative cost performance index (CPIC).

EAC using a new estimate. EAC equals the actual costs to date (AC^c) plus a new ETC is provided by the performing organization.

Formula: EAC=AC^c + ETC

Conclusion

In this article, I have delved into the important points of project cost management. Without proper planning of cost management, deliverables may happen, but chances of over shooting the budget always remain. So it is very critical that we need to keep a strict vigil on various processes involved in estimation, budgeting and control in a project so as to ensure its completion within the allotted time frames and budget.



User Comments

Title: 2012 NFL jerseys   
Name: NIKE NFL jerseys
Date: 2012-05-20 11:38:12 PM
Comment:
[/pre]Cheap NFL,NBA,MLB,NHL
[url=http://www.jersey2shop.com/]Jerseys From China[/url]
[url=http://www.jersey2shop.com/]2012 nike nfl Jerseys[/url]
[url=http://www.jersey2shop.com/]cheap China Jerseys[/url]
[url=http://www.jersey2shop.com/]Sports Jerseys China[/url]
[url=http://www.jersey2shop.com/NFL-Jerseys-c68/]NFL Jerseys China[/url]
[url=http://www.jersey2shop.com/NBA-Jerseys-c77/]NBA Jerseys China[/url]
NHL Jerseys China
[url=http://www.jersey2shop.com/MLB-Jerseys-c94/]MLB Jerseys China[/url]NFL jerseys For Sale online.All Our Jerseys Are Sewn On and Directly From Chinese Jerseys Factory
[/pre]
[pre]We Are Professional China jerseys Wholesaler
[url=http://www.cheapjersey2store.com/]Wholesale cheap jerseys[/url]Cheap mlb jerseys
[url= http://www.cheapjersey2store.com/]2012 mlb all atar jerseys[/url]
[url= http://www.cheapjersey2store.com/ [/url]Cheap China Wholesael[/url]
[url= http://www.cheapjersey2store.com/]Wholesale jerseys From China[/url]
[url=http://www.cheapjersey2store.com/]2012 nike nfl Jerseys[/url]Free Shipping,Cheap Price,7 Days Deliver
[/pre]
[/pre]
We are professional jerseys manufacturer from china,wholesal
sports [url= http://www.cheapjersey2store.com/]Jerseys From China[/url]
[url=http://www.cheapjersey2store.com/NFL-Jerseys-c68]NFL jerseys China[/url]
[url=http://www.cheapjersey2store.com/NHL-Jerseys-c96/]NHL Jerseys China[/url]
[url=http://www.cheapjersey2store.com/NBA-Jerseys-c77/]NBA Jerseys China[/url]
[url=http://www.cheapjersey2store.com/MLB-Jerseys-c94/]MLB Jerseys China[/url]
[url= http://www.cheapjersey2store.com/]China Jerseys[/url],Free Shipping
[/pre]
[/pre]
We are professional jerseys manufacturer from china,wholesal
sports [url= http://www.jerseycaptain.com/]cheap jerseys sale online [/url]
[url= http://www.jerseycaptain.com/]2012 nike nfl Jerseys[/url]
[url=http://www.jerseycaptain.com/NFL-Jerseys-c68]cheap NFL jerseys China[/url]
[url=http://www.jerseycaptain.com/NHL-Jerseys-c96/]NHL Jerseys C
Title: Software Project Estimation   
Name: Nikko Quilisadio
Date: 2011-11-09 6:51:43 AM
Comment:
Can you give me a Sample format of Software Project Estimation..,
any Format would do.

tnx
Title: cost istimation   
Name: helth club
Date: 2011-05-13 12:24:49 AM
Comment:
how decide the project cost on which base please send information on anandshindepatil@rediffmail.com
Title: cost estimation project   
Name: yahye haybe omar
Date: 2010-11-29 9:42:29 AM
Comment:
plz give one example of cost estimation
Title: Quantity Surveyor   
Name: Tayebwa Duncan
Date: 2010-11-24 7:49:08 AM
Comment:
The Topic was well discussed. However, i wish you could give details of the cost control process based on an hypothetical example,the ways and means and the challenges expected to be met in the process.

Thank you once again
Title: cost estimation   
Name: Gloria Thomas
Date: 2010-11-23 8:46:39 PM
Comment:
Great information. I read about Hybrid: Phase estimating by Larson and Gray and was wondering where does it fit in the category discussed here
Title: cost estimating and budgeting   
Name: PCC Student
Date: 2010-10-07 12:11:39 AM
Comment:
Base in the actual society, their are lots of project baseline which involved cost estimating and budgeting. This kind of strategy are very applicable to the business project management.
Title: CIVIL ENGINEER   
Name: PETETI SUBBARAYUDU
Date: 2010-09-22 1:01:37 AM
Comment:
GOOD EXPLANATION.ONE SUGGETION ACCORDING TO MY KNOLDGE PLS GIVE ONE EXAMPLE OF BUILDING COSTING
Title: Quantity Surveyor   
Name: Cris
Date: 2010-06-17 9:46:11 PM
Comment:
Great info... I would be glad if you can send me a manhour table for computing the labor cost of a construction project of a multi-storey building that is applicable in the Philippines.
Title: cost engineer   
Name: manish
Date: 2010-04-05 9:16:33 AM
Comment:
very well explained but should add more engineering based case studies if u peopkle find anything related to cost estimation pls forward to shingala_manish2000@yahoo.com
Title: Project Cost Estimation   
Name: Shekar
Date: 2010-03-18 2:25:21 AM
Comment:
Thank you. Good Explanation. A few examples would be great. if any particular templates with this will be more value added.
Once again Thank you very much.

Thanks,
Shekar.K
Title: Project Cost Estimation   
Name: Kuldeep Shige
Date: 2010-03-10 9:00:53 AM
Comment:
well explained post for Project Cost Estimation;
Title: cost easimating   
Name: ashok bahuguna
Date: 2009-12-25 8:49:55 AM
Comment:
Kindly explaine me about cost eastimation
Title: cost estimation   
Name: rupali
Date: 2009-09-27 4:26:06 AM
Comment:
excellent...!!!!!!!!! :)
Title: Assistant Professor   
Name: D Bhattacharya
Date: 2009-08-27 2:44:44 AM
Comment:
Thank you for the great insight of the subject.Please do give us some more knowledge about project management.

Regards
Title: Cost Estimation   
Name: Ali
Date: 2009-05-03 4:08:28 PM
Comment:
Good explanation.
Title: Research Scholar   
Name: Jagannath Malllick
Date: 2009-03-30 3:26:02 AM
Comment:
The article is very excellent. Please provide one example.

Thanks
Jagannath
Title: Project Manager   
Name: Ritesh Lakhani
Date: 2008-10-07 10:55:23 AM
Comment:
Ultimate article, involves everything related to cost of project in a small and single article. good one.
Title: Costestimation Comment   
Name: Mohitraj
Date: 2008-05-21 8:25:08 AM
Comment:
We feel proud after take a look on this topic but u should need to expaned in the detail of the given topic.............!!!!!!!!!
Title: Proect Planning and management consultant   
Name: S Vijaya Bhaskar
Date: 2008-04-26 8:12:24 PM
Comment:
Clear Explanation. Hats off to Arindam Ghosh.
Title: mba   
Name: venicia
Date: 2008-04-13 1:14:53 PM
Comment:
thank you,good information
Title: kumai   
Name: indra
Date: 2008-03-27 4:21:41 AM
Comment:
very good site
Title: teacher   
Name: madina
Date: 2008-02-22 1:25:57 AM
Comment:
very clear explanations.
Thank you.
Title: MBA 08   
Name: Kevin
Date: 2008-02-01 11:04:18 PM
Comment:
Well-explained. Thank you.

Kevin
Title: Project Manager   
Name: Vasoula Christoforides
Date: 2007-12-17 4:44:52 PM
Comment:
Your article is very informative. Successful Estimation is not simple, your article has provided a better understanding. A few examples would be great. Thank you
Title: Cost estimation   
Name: Hariharan
Date: 2007-10-15 1:57:57 PM
Comment:
Really very impressive. Good Arindam. Apart from a conceptual, If any practical sample documents / Templates added with this will be more value added.
If any one of you have such things pl. send across to nhariharann@rediffmail.com

Many thanks again to Arindam Ghosh...
Hari
Title: Manager   
Name: Neelakandan
Date: 2007-10-07 2:39:05 PM
Comment:
I read the document and was very impressed. I want one Example for the Estimation, kindly send as the earliest.
Thanks
Neelakandan
Title: Consultant   
Name: sankar jayaram
Date: 2007-08-15 11:28:16 PM
Comment:
Excellent ..
jshankar.2002@gmail.com
Title: Project Cost Management   
Name: Rahul Gurchal
Date: 2007-06-09 2:01:20 AM
Comment:
Hello,
I read the document and was very impressed with the kind of depth the topic was covered with.I thank you for the great insight i received from your article on this topic.

Thanks & regards,
Rahul Gurchal,

Savoir Faire Management Solutions Pvt Ltd,
New mumbai, Vashi sector 17.
Title: GIVE SOME PRACTICAL EXAMPLE OF PROJECT COST ESTIMATION   
Name: P.C.E
Date: 2007-02-17 12:30:47 PM
Comment:
GIVE SOME PRACTICAL EXAMPLE OF PROJECT COST ESTIMATION

Product Spotlight
Product Spotlight 





Community Advice: ASP | SQL | XML | Regular Expressions | Windows


©Copyright 1998-2024 ASPAlliance.com  |  Page Processed at 2024-04-28 6:52:49 AM  AspAlliance Recent Articles RSS Feed
About ASPAlliance | Newsgroups | Advertise | Authors | Email Lists | Feedback | Link To Us | Privacy | Search