All quality control tools and techniques may be used in
Quality Assurance process.
Outputs of a typical Perform Quality Assurance:
Requested Changes
Changes that improve the quality of the project, both
technical and organizational are the key output of quality assurance.
Recommended Corrective Actions
Actions that improve the efficiency and effectiveness of the
project and the organization are a result of QA activities such as audits.
Updates the Organizational Process Assets (Updates).
All standards, rule and regulations are updates as a result
of any analysis of the QA activities. These quality standards are used during
the Perform Quality Control Process.
Updates the Project Management Plan
Any update to the Quality Management Plan requires an update
to the project management plan. Existing processes may be updated, process
improvements may be implemented and Requested changes (additions,
modifications, deletions) to the project management plan and its subsidiary
plans are processed by review and disposition through the Integrated Change
Control process.